Project Lighthouse, being developed by Vantage in Port Washington with Oracle as tenant, faces a real risk of slipping beyond Oracle's target of delivering capacity to customers in the second half of next year, according to research firm Aterio.
The immediate obstacle is American Transmission Company's (ATC) application to the Public Service Commission of Wisconsin (PSC) for approval to build the campus's grid connection. The PSC closed the original case after withdrawing its finding that the application was complete; ATC refiled in September, restarting the approval process.
"The problem is power. The campus cannot run until ATC connects it to the grid, and ATC cannot start building until the PSC approves its application," Aterio said.
ATC is planning more than $2 billion in transmission infrastructure tied to datacenter developments across Wisconsin, ranging from high-voltage power lines and substations to upgrades of existing facilities.
Aterio's base case puts partial power in December 2027 and full supply in October 2028. An extended regulatory review could push those dates to June 2028 and April 2029. Even December 2027 power delivery would leave little room for testing and commissioning before Oracle's deadline, with the campus's load expected to ramp up mainly from the first quarter of 2028.
The campus is rated at 902 MW of computing load and 1.3 GW of total electricity demand. Oracle could face more than $100 million a year in financing costs to guarantee the power commitments behind the project, according to earlier reporting.
Separately, Bloomberg reported that Oracle sent a force majeure notice to a Blue Owl Capital subsidiary developing Project Jupiter in New Mexico, seeking to defer payments if the campus failed to come online as planned rather than withdraw from the project. Oracle says the development remains on schedule.
The Financial Times reported that Tencent has signed a $7 billion deal to lease around 100,000 AI processors from Oracle. For context, Oracle reported $55.7 billion in total capital expenditures for fiscal 2026, which closed at the end of May, against total revenue of $67.4 billion. Capex guidance for the 2027 financial year is up to $95 billion.