The nature adviser urged Bristol city council not to grant planning permission for a 40MW datacentre at Avonmouth, warning it could cause “disturbance and displacement” to rare and vulnerable bird species in the Severn estuary special protection area, within 600 metres of the site. Another protected site, Hallen Marsh, was only 270 metres away but had not been accounted for by developers when assessing noise pollution, Natural England said.
The Environment Agency, also threatened with abolition by the de facto deputy prime minister, Louise Haigh, objected over flooding risk at the site, which is on a high-risk flood plain, expressing concern that people would not be able to take safe refuge in the event of a deluge. The agency said developers had not provided information on water use or the risk of pollution from land contamination to controlled waters.
Haigh this week blamed quangos, including Natural England, for blocking development and indicated both bodies could be scrapped, with their responsibilities handed to ministers or devolved. Ministers are pushing for AI datacentres as key to growing the UK economy. Hundreds are planned, with more than 300 waiting to connect to the electricity grid, representing 73GW of demand, almost double the peak winter energy demand for the entire UK.
Government sources denied that the Avonmouth objection or Natural England's stance on taking a precautionary approach to widespread datacentre construction had influenced Haigh’s announcement.
Craig Bennett, the chief executive of the Wildlife Trusts, said the threatened abolition was a worrying sign of an attack on environmental regulation. “Regulatory arm’s-length bodies like Natural England are set up to implement the law of parliament,” he said. “If we want decisions made about nature on the basis of science rather than the very last private corporate or vested interest that a minister has spoken to, then we have independent arm’s-length bodies like Natural England.”
Mary Stevens, an AI campaigner at Friends of the Earth, said: “Natural England was doing its job brilliantly here as an independent adviser. I would have no confidence if this was a government minister doing the work because they would not be acting independently to protect nature.”
Rivington Energy, the developer, said it acknowledged feedback from the Environment Agency and Natural England and welcomed the opportunity to continue working constructively with all consultees throughout the planning process. It said additional studies were being prepared and a detailed environmental statement would support the next stage of project assessment.
More than 4,000 people have objected to the datacentre’s construction. Bristol council said the proposal was “likely to give rise to significant environmental effects” and wanted a full environmental impact assessment.
A government spokesperson said: “Datacentres are essential to our economy, but their development must protect the environment and benefit local communities. Developers must meet planning requirements, with local authorities assessing environmental impacts, and then deciding on local applications.”