The NIAO found that the contractor, previously reported by the BBC as Worldwide Environmental Products Inc. (WEP Inc), fell six weeks behind schedule just six months after winning the contract in 2019. The Driver and Vehicle Agency (DVA) issued two formal warnings and moved to terminate the deal. The company won a High Court challenge, with a judge ruling that the contract did not specify clear dates for implementing key systems. The contract was eventually terminated ahead of a second court case in April 2025, and WEP Inc was paid £1.5 million to go away, an amount described as “a significant fruitless expenditure”. A further £3.6 million was spent on the project.
The report also highlighted flaws in the original procurement. WEP Inc's tender was priced at £10.8 million, 53% lower than the only other compliant bid and 40% below the DVA's own business case estimate. The NIAO said that while correct processes were followed, the checks did not provide sufficient assurance the solution could be delivered at that price, and noted limited scrutiny of the proposed IT solution.
Carville said the DVA and Stormont's Central Procurement Directorate have identified lessons and that there is evidence these have been acted upon to improve subsequent procurement exercises. She added: “It is vital that learning is shared beyond these two organisations, particularly as today's findings echo those in previous reports by the NIAO on the delivery of major IT projects.” A replacement contract for the testing centres was awarded in March this year at a value of £46 million, with completion expected in mid-2029. The report notes direct comparison with the original bid is difficult because of changes in project scope, implementation assumptions and contract lifespan.
A spokesperson for the Department for Infrastructure said: “The Department welcomes the publication of the NIAO Report and is considering the findings. No further comment will be made until the Assembly process is complete.” WEP Inc said it did not accept any criticism contained in the report, stating: “It is surprising that the NIAO did not seek our input into the report during its preparation, nor any insights from us as to how our experience of successful delivery of projects in other countries has compared to our experience of trying to deliver a project of this nature in Northern Ireland.”