The Nuclear Regulatory Commission has issued a construction permit for four advanced nuclear reactors at a Dow petrochemical complex on the Texas Gulf Coast, advancing a flagship project under the U.S. Energy Department’s program to revive the nation’s nuclear sector.
The Long Mott Generating Station, developed by chemical giant Dow and nuclear startup X-energy, is planned to use small, modular reactors that can be produced in factories and assembled on site. Dow plans to install four 80-megawatt reactors; the Xe-100 uses helium gas as coolant rather than water and a pelletized fuel form.
The project was selected in 2020 for the Energy Department’s Advanced Reactor Demonstration Program. “This milestone marks a significant step forward,” Mike Goff, principal deputy assistant secretary for nuclear energy, said in a press release. “The NRC’s approval demonstrates meaningful progress toward deploying advanced reactors.”
The NRC granted the permit after an expedited 18-month review under executive orders from President Donald Trump aimed at accelerating the national energy sector. NRC Chairman Ho K. Nieh said in a press release: “We delivered on the 18-month schedule, proving we can do rigorous safety reviews on predictable timelines.”
Dow must still make a final decision to proceed; if it does, construction could begin before 2030. If successful, the project could provide a model for other industries to install dedicated, on-site power generation, said Martin O’Neal, general counsel for the Nuclear Energy Institute. “The nuclear industry is watching this project very closely,” he said.
The reactors use a fuel form called TRISO. X-energy CEO J. Clay Sell has described the Xe-100 as “physically impossible to melt down.” The NRC’s Mehdi Reisi Fard, deputy director of advanced reactors, said functional containment is less reliant on pumps or human intervention to mitigate anomalies than current control systems.
But critics remain skeptical. Diane Wilson, director of San Antonio Bay Waterkeeper and a retired shrimper from the nearby town of Seadrift, called the project “outrageous,” noting that spent fuel will be stored indefinitely on site because the United States lacks a permanent disposal site. Her organization filed legal challenges to the project’s permit application in 2025 that were dismissed by the NRC.
Edwin Lyman, director of nuclear power safety at the Union of Concerned Scientists, questioned the safety claims. “It’s just a myth that this fuel is indestructible or meltdown-proof,” he said. “This fuel has vulnerabilities.”
The United States has built only one new nuclear power plant in the past three decades. The NRC issued its first permit for an advanced test reactor in 2023 and its first permit for an advanced commercial reactor in March 2026.
Analysis
Why This Matters
- The permit marks the first approval for an advanced commercial reactor at an industrial site, potentially enabling a model for companies to add dedicated nuclear power to their operations.
- It tests the viability of small modular reactors to revive the U.S. nuclear industry after decades of high costs and delays.
- The approval process highlights tensions between fast-tracking energy projects and addressing unresolved safety and waste concerns.
Background
The United States has built only one new nuclear power plant in the past 30 years, as traditional large-scale projects became prohibitively expensive and slow. In 2020, the Energy Department launched the Advanced Reactor Demonstration Program to support next-generation designs that are smaller and cheaper. The Dow-X-energy project was one of two flagship initiatives selected.
Key Perspectives
U.S. Energy Department and Nuclear Regulatory Commission: view the approval as a demonstration that advanced reactors can be licensed quickly while maintaining safety standards.
Dow and X-energy: express confidence in the technology, emphasizing the inherent safety of the Xe-100 design and its potential to provide reliable power for industrial sites.
Diane Wilson / San Antonio Bay Waterkeeper: opposes the project over the lack of a permanent nuclear waste repository and the indefinite storage of spent fuel on site.
Edwin Lyman / Union of Concerned Scientists: questions the claim that TRISO fuel is meltdown-proof, arguing that the fuel has vulnerabilities and that eliminating physical containment carries risks.
What to Watch
- Dow’s final investment decision, which will determine whether construction begins in the coming years.
- Potential further legal action from environmental groups, who have already challenged the project.
- The project’s progress as a bellwether for other advanced reactor proposals in the United States.
Checked
12 claims in this story checked against 1 source: 11 supported.
Show each claim
- SupportedThe NRC approved a construction permit for four advanced reactors at a Texas Gulf Coast petrochemical complex.Texas Tribune: “The Nuclear Regulatory Commission this week issued a permit for construction of four next-generation nuclear reactors at a petrochemical complex on the rural Gulf Coast of Texas.”
- SupportedThe Dow–X-energy project is among the first to receive a permit for a next-generation design.Texas Tribune: “The NRC issued its first permit for construction of an advanced test reactor in 2023, and its first permit for an advanced commercial reactor in March 2026.”
- SupportedThe Long Mott project is one of two flagship projects selected in 2020 for the Energy Department’s Advanced Reactor Demonstration Program.Texas Tribune: “The Long Mott Generating Station, developed by chemical giant Dow and nuclear startup X-energy, is one of two flagship projects selected by the U.S. Energy Department in 2020 for its Advanced Reactor Demonstration Program”
- SupportedMike Goff said, “This milestone marks a significant step forward” and “The NRC’s approval demonstrates meaningful progress toward deploying advanced reactors.”Texas Tribune: ““This milestone marks a significant step forward,” Mike Goff, principal deputy assistant secretary for nuclear energy, said in a press release Monday. “The NRC’s approval demonstrates meaningful progress toward deploying advanced reactors.””
- SupportedDow plans four 80-megawatt reactors, and the Xe-100 uses helium gas for cooling and pelletized fuel.Texas Tribune: “Dow plans to install four 80-megawatt reactors by X-energy at its Seadrift Operations complex”
- SupportedThe NRC completed an expedited 18-month review under executive orders from President Donald Trump aimed at accelerating the national energy sector.Texas Tribune: “The agency approved Dow’s reactor construction permit after an expedited review under executive orders from President Donald Trump aimed at accelerating the national energy sector.”
- Partly supportedNRC Chairman Ho K. Nieh said, “We delivered on the 18-month schedule, proving we can do rigorous safety reviews on predictable timelines.”Texas Tribune: ““We delivered on the 18-month schedule, proving we can do rigorous safety reviews on predictable timelines that move advanced nuclear technology from design to construction,” said NRC Chairman Ho K. Nieh in a press release.”
- SupportedDow must make a final decision to proceed, and construction could begin before 2030 if it proceeds.Texas Tribune: “Dow still needs to make a final decision to proceed with the project, the company said in a release. If it does, construction could begin before 2030.”
- SupportedMartin O’Neal said the project could provide a model for other industries to install dedicated on-site power generation.Texas Tribune: “If the project proves successful, it would “provide a pathway other industries can emulate” to install dedicated, onsite power generation, said Martin O’Neal, general counsel for the Nuclear Energy Institute”
- SupportedDiane Wilson said the project was “outrageous” and noted that spent fuel would be stored indefinitely on site because the United States lacks a permanent disposal site.Texas Tribune: ““Frankly, it’s outrageous,” she said. “This is outrageous.” Spent fuel from the reactors will be stored indefinitely on-site as nuclear waste, she noted, as the U.S. still lacks a permanent national disposal site.”
- SupportedWilson’s organization filed legal challenges to the permit application in 2025, and the NRC dismissed them.Texas Tribune: “In 2025, Wilson’s organization filed legal challenges to the project’s permit application over safety concerns, which were ultimately dismissed by the NRC.”
- SupportedThe United States built only one new nuclear power plant in the past three decades.Texas Tribune: “In the last three decades, the U.S. has built just one new nuclear power plant”