Queensland Deputy Premier Jarrod Bleijie has announced a new construction code, introduced in response to the CFMEU inquiry, will be retrospectively applied to the 17 Brisbane 2032 Olympic venues GIICA will deliver, as early excavation at the Victoria Park stadium site marks its 100th day.
Speaking at the Victoria Park site on Wednesday, Bleijie said the Games Independent Infrastructure and Coordination Authority (GIICA) had requested the new productivity code be applied to the venues it will deliver. The code, adopted by the Queensland government on Tuesday, sets mandatory workplace, safety and industrial relations standards for publicly funded construction projects of $150 million and more.
Under the new rules, unions are banned from forcing contractors to display flags and branding on sites. "If you're a new worker and you rock up and you are not a member of the CFMEU, the flags on the construction site are a sign you will not enter this construction site unless you are a member," Bleijie said. "And if they get there, they get bullied into joining the CFMEU. That's not freedom of association."
The code is prospective, but line agency ministers or agencies seeking to apply it to current tenders have to write to the responsible minister for approval. GIICA made that request on Tuesday, and Bleijie approved it by the evening.
The CFMEU has already vowed to build the new Brisbane Stadium, expected to begin construction by mid-2027, due to its existing enterprise agreement with preferred builders BESIX Watpac and John Holland.
Stephen Conry, chair of GIICA, said about 200,000 cubic metres of soil had been moved in the first 100 days of the early works program at the stadium site. About 65 workers had been on site six days a week, weather permitting, to prepare the ground. "The cut-and-fill approach that we've adopted for the site has been very effective, very productive, and necessary when you look at the naturally hilly topography which surrounds us, and also to minimise traffic movements or truck movements from the site," he said.
The project validation report for Victoria Park is due in the first half of 2027, after which construction could commence. Community consultation for the precinct master plan, undertaken by Arup, has concluded. Arup's Penny Hall said more than 42,000 people had logged into the Victoria Park precinct website. Hall said the master plan was a "living document" and changes to the draft plan released in August were yet to be finalised.
On transport, Bleijie said Exhibition Station would be in use during the Games, despite IOC concerns about its proximity to the planned athletes' village. Pedestrian access from Fortitude Valley station, where many spectators would walk after pre-event food and drinks, remained an issue. Hall said the project was working with Brisbane City Council on the "last mile" to the precinct.
Analysis
Why This Matters
- The retrospective application of the code could disrupt existing enterprise agreements with builders and unions, potentially affecting construction timelines for Olympic venues.
- The ban on union flags and branding aims to address Coalition claims of coercion on worksites, reshaping industrial relations on major projects.
- With the first major venue excavation underway, delivery of the 2032 Games hinges on completing planning and securing builder contracts without delays.
Background
The new productivity code was adopted by the Queensland government on Tuesday in response to the CFMEU inquiry. It sets standards for workplace, safety and industrial relations on publicly funded projects worth $150 million or more. The code includes a provision for prospective application but allows retrospective application if ministers approve. GIICA requested the code be applied to all 17 venues it is delivering.
Key Perspectives
- Deputy Premier Jarrod Bleijie: Says the code is needed to prevent unions from coercing workers through flag displays, and that GIICA's request for retrospective application ensures the new standards cover major Olympic tenders.
- CFMEU: The union has vowed to build the new Brisbane Stadium under its existing enterprise agreement with preferred builders, indicating it will resist the new code's impact on its arrangements.
What to Watch
- The project validation report for Victoria Park, due in the first half of 2027, which will clear the way for stadium construction.
- Whether the CFMEU challenges the retrospective application of the code through legal or industrial action.
- Completion of the precinct master plan, expected after public feedback is consolidated, which will shape the final design of the stadium and surrounding venues.
Checked
12 claims in this story checked against 1 source: 12 supported.
Show each claim
- SupportedThe new construction code will be applied retrospectively to Brisbane 2032 Olympic venues GIICA will deliver.Sydney Morning Herald - Latest News: “A new construction code introduced in response to the CFMEU inquiry will be retrospectively applied to Brisbane 2032 Olympic venues”
- SupportedThe code will apply to 17 venues GIICA will deliver.Sydney Morning Herald - Latest News: “GIICA had asked that the new code be applied to the 17 venues it will deliver.”
- SupportedThe stadium excavation has reached its 100th day.Sydney Morning Herald - Latest News: “as he marked 100 days of excavation at Victoria Park.”
- SupportedBleijie announced the code in response to the CFMEU inquiry.Sydney Morning Herald - Latest News: “A new construction code introduced in response to the CFMEU inquiry will be retrospectively applied to Brisbane 2032 Olympic venues, Deputy Premier Jarrod Bleijie said on Wednesday”
- SupportedBleijie said non-CFMEU workers could be barred from entering a site and bullied into joining the union.Sydney Morning Herald - Latest News: “If you’re a new worker and you rock up and you are not a member of the CFMEU, the flags on the construction site are a sign you will not enter this construction site unless you are a member”
- SupportedThe code sets mandatory workplace, safety and industrial-relations standards for publicly funded construction projects worth $150 million or more.Sydney Morning Herald - Latest News: “sets mandatory workplace, safety, and industrial relations standards for publicly funded construction projects of $150 million and more.”
- SupportedThe code is prospective, but ministers or agencies can seek approval to apply it to current tenders.Sydney Morning Herald - Latest News: “it’s prospective – it’s going forward. But if line agency ministers or agencies wanted the code to apply to current tenders, they have to write to the responsible minister for approval.”
- SupportedGIICA requested the code’s application on Tuesday, and Bleijie approved it by that evening.Sydney Morning Herald - Latest News: “GIICA did that yesterday. By yesterday afternoon or last evening, I’d written back to GIICA and approved that.”
- SupportedThe CFMEU has vowed to build the new Brisbane Stadium because of its existing enterprise agreement with preferred builders BESIX Watpac and John Holland.Sydney Morning Herald - Latest News: “The CFMEU has already vowed to build the new Brisbane Stadium – for which construction was expected to begin by mid-2027 – due to its existing enterprise agreement with preferred builders BESIX Watpac and John Holland.”
- SupportedConstruction of the new Brisbane Stadium was expected to begin by mid-2027.Sydney Morning Herald - Latest News: “for which construction was expected to begin by mid-2027”
- SupportedAbout 200,000 cubic metres of soil had been moved during the first 100 days of early works at the stadium site.Sydney Morning Herald - Latest News: “in the first 100 days of the early works program at the Brisbane Stadium site, about 200,000 cubic metres of soil had been moved.”
- SupportedConry said about 65 workers had been on site six days a week, weather permitting, to prepare the ground.Sydney Morning Herald - Latest News: “About 65 workers had been at the site six days a week, weather permitting, to prepare the ground for the stadium’s construction.”