Oracle Sends Force Majeure Notice on New Mexico Stargate Data Center

Notice allows payment delays if project misses 2028 target; company says schedule remains on track

By LineZotpaper
Published
Read Time2 min
Sources2 outlets
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate AI data center campus in New Mexico, a move that would allow the company to delay payments should the facility miss its 2028 target. The notice comes amid a series of setbacks tied to energy supply, including delays to a gas pipeline and a pending air-quality permit.

Oracle sent the force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday. Force majeure clauses, common in energy and commodities contracts, excuse a party from obligations when events outside its control interfere. According to Bloomberg's sources, Oracle is not seeking to exit as the campus's main tenant; instead, the notice would allow payment delays if the facility misses its 2028 target.

Oracle maintains it does not expect a delay. "Project Jupiter remains on our planned schedule," the company said in a statement to CNBC. "We are fully committed to New Mexico and confident in our path forward."

Blue Owl Capital, whose unit received the notice, said in its own statement to CNBC that "this notice does not change the financial commitments to this multi-year project."

The notice follows a string of setbacks at the site, many tied to its energy supply. The campus, designed to handle 2.45 gigawatts, is meant to run on gas-powered fuel cells from Bloom Energy. An Energy Transfer pipeline intended to deliver gas has been delayed nearly six months, to February 1, 2027, after regulators repeatedly denied permits. In August, Bloomberg reported the pipeline's route had been changed after those rejections. A separate air-quality permit for the fuel cell system is also pending, with a November 23 deadline for the state’s environment department.

Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI, and SoftBank announced with President Donald Trump early in his second term. The campus has drawn opposition from residents and environmental groups and has become a political flashpoint ahead of the midterm elections. Oracle has responded with a public outreach campaign aimed at winning over critics, according to Bloomberg.

§

Analysis

Why This Matters

  • The Stargate project is a key part of the Trump-era AI infrastructure push. Delays could slow AI compute capacity for OpenAI and others.
  • Energy supply challenges highlight the tension between AI's growing power demands and regulatory hurdles.
  • The notice signals potential cost overruns or timeline slippage, which could affect investor confidence in large-scale AI data center builds.

Background

Project Jupiter is part of Stargate, a massive AI infrastructure initiative announced in early 2026 by Oracle, OpenAI, and SoftBank with the Trump administration. The New Mexico campus is designed to consume 2.45 gigawatts and relies on natural gas-fueled Bloom Energy fuel cells. Force majeure clauses are common in energy contracts; invoking one allows a party to avoid penalties for delays beyond its control. The notice here appears protective rather than an exit signal.

Key Perspectives

Oracle: The company says the project remains on schedule and it is fully committed to New Mexico. The force majeure notice is likely a financial safeguard in case of external delays. Blue Owl Capital: The developer receiving the notice insists that financial commitments to the multi-year project remain unchanged. Critics and opponents: Local residents and environmental groups have opposed the campus, citing environmental and infrastructure concerns. The project has become a political flashpoint ahead of midterm elections.

What to Watch

  • The November 23 deadline for the air-quality permit from New Mexico's environment department.
  • Progress on the Energy Transfer pipeline, now expected by February 1, 2027.
  • Oracle's public outreach campaign and any further regulatory or legal challenges.