Queensland accounts for half of Australia's proposed onshore wind power capacity, with $5.8 billion worth of projects securing funding or starting construction, according to the Clean Energy Council's latest report. The state has the longest average completion time, at about three years.
Most Queenslanders will not see any of the state's 543 wind turbines on their daily commute; you have to drive almost three hours out of Brisbane to rural areas to see one. If all approved projects proceed, installed wind capacity could reach about one and a half times Queensland's current coal-fired power capacity, treasury figures show.
Experts attribute the slow progress to multiple factors, including community opposition and planning uncertainty. Former Origin Energy executive Tony Wood, now a Grattan Institute senior fellow, said community angst, policy uncertainty, slow transmission build-out, and higher construction costs were among the causes.
"We've got a very large pipeline, but blocked pipelines don't flow very well," he said.
The Crisafulli government recently changed planning rules to require wind and solar developers to conduct social impact assessments and secure community benefit agreements, similar to fossil fuel projects, and cancelled two major wind projects, Moonlight Range and Forest Wind, which combined could have powered about 760,000 homes. Wood said the government had also abandoned renewable energy targets without clearly explaining its position on renewables, frustrating investors.
Treasurer and Energy Minister David Janetzki said the government had an "open for business approach" and encouraged private investment in new generation. "Our Energy Roadmap is about economics and engineering over ideology, coal for longer, more gas and private sector investment into renewables," he said in a statement.
Cattle farmer Glen Franz, who has about 13 turbines within three kilometres of his property north of Dalby, said he was not anti-renewable but opposed wind farms near residential dwellings. "Obviously, there's a place for it, but it's not in these built-up areas, it's too closely settled," he said.
Queensland has 10 operating wind farms with more than 500 turbines, and 17 projects approved or under construction. The largest operational is the 923MW MacIntyre Wind Farm near Warwick, which can produce enough electricity to power about 620,000 homes. The biggest planned are Bungaban Wind Farm in the Western Downs and Wongalee Wind Energy Project west of Townsville, each of which could generate up to 1,400MW. Once complete, the total turbine count could reach 1,383.
By comparison, the United Kingdom, more reliant on wind power, has 7,353 onshore turbines in an area seven times smaller than Queensland.
Queensland Renewable Energy Council chief executive Katie-Anne Mulder said developers needed to consult communities and "work hard to earn their trust." She noted that 82 per cent of respondents to a survey believed the government's Energy Roadmap needed improvement for greater certainty, warning that "Queensland really risks missing out on those billions of dollars in private investment."
Wood said increased renewable generation had put downward pressure on wholesale electricity prices, but new transmission and storage, plus coal plant closures, could push prices back up. "Even though the cost of producing electricity from wind and solar is cheaper than coal, by the time you get it to where we need it, it's not much cheaper," he said. He added that building renewables fast enough to address climate change while maintaining reliable, affordable power was a challenge. "If we go too fast, we'll almost certainly muck it up and that's not good. But if we go too slow, climate change will eventually take over."
Analysis
Why This Matters
- Queensland holds half of Australia's onshore wind pipeline, making its pace of development critical to national renewable energy targets and power prices.
- Slow completion times and policy uncertainty risk losing billions in private investment, affecting jobs and energy transition.
- Community opposition and planning changes could set a precedent for how other states balance renewable expansion with local concerns.
Background
Queensland's wind energy sector has grown significantly over the past decade, with the state's best wind resources in rural areas west of Brisbane. The Crisafulli government's Energy Roadmap, favouring coal, gas, and private renewable investment, has replaced earlier renewable targets, creating uncertainty. The Clean Energy Council report tracks Australia's wind pipeline, highlighting Queensland's leading share but slowest build rates.
Key Perspectives
Tony Wood (Grattan Institute senior fellow): attributes delays to community angst, policy uncertainty, slow transmission build-out, and higher construction costs, warning the pipeline may remain "plugged."
David Janetzki (Queensland Treasurer and Energy Minister): says the government encourages private investment, with an "open for business approach" based on economics and engineering over ideology.
Glen Franz (cattle farmer): says he is not anti-renewable but opposes wind farms near homes, advocating they be placed in less populated areas.
Katie-Anne Mulder (Queensland Renewable Energy Council CEO): says developers must earn community trust, and the industry needs greater policy certainty to avoid missing investment.
What to Watch
- Whether the Crisafulli government provides clearer direction on renewables in its Energy Roadmap.
- How the community benefit agreements and social impact assessments affect the pace of new project approvals.
- Potential cancellation or delay of major projects like Bungaban and Wongalee wind farms.
Checked
11 claims in this story checked against 1 source: 9 supported.
Show each claim
- SupportedQueensland accounts for half of Australia’s proposed onshore wind capacity.Just In: “Queensland now accounts for half of Australia's proposed onshore wind power capacity”
- SupportedQueensland has the longest average onshore wind project completion time, at about three years.Just In: “Queensland has the longest average onshore wind project completion time of any state, at about three years.”
- Partly supportedQueensland’s installed wind capacity could reach about one and a half times its current coal-fired power capacity.Just In: “the state's installed wind capacity could become about one and a half times more than the existing coal-fired power capacity”
- SupportedThe projects securing funding or starting construction are worth $5.8 billion.Just In: “with $5.8 billion worth of projects securing necessary funding or starting construction”
- SupportedExperts cite community opposition and planning uncertainty among the factors slowing progress.Just In: “Experts have put this down to multiple factors including community opposition and planning uncertainty.”
- SupportedTony Wood said, “We've got a very large pipeline, but blocked pipelines don't flow very well.”Just In: “"We've got a very large pipeline, but blocked pipelines don't flow very well," he said.”
- SupportedJanetzki said, “Our Energy Roadmap is about economics and engineering over ideology, coal for longer, more gas and private sector investment into renewables.”Just In: “"Our Energy Roadmap is about economics and engineering over ideology, coal for longer, more gas and private sector investment into renewables," he said in a statement.”
- SupportedThe government changed planning rules requiring social impact assessments and community benefit agreements, and cancelled Moonlight Range and Forest Wind, projects with potential to power about 760,000 homes combined.Just In: “The Moonlight Range and Forest Wind projects had the potential to power about 760,000 homes combined, but the government intervened with call-in powers.”
- SupportedGlen Franz said, “Obviously, there's a place for it, but it's not in these built-up areas, it's too closely settled.”Just In: “"Obviously, there's a place for it, but it's not in these built-up areas, it's too closely settled," he said.”
- SupportedQueensland has 10 operating wind farms and 17 projects approved or under construction.Just In: “Queensland has 10 operating wind farms with a total of more than 500 turbines, and an additional 17 projects that have been approved or are under construction.”
- Partly supportedCoal plant closures could push electricity prices back up, alongside new transmission and storage.Just In: “new transmission lines and energy storage, alongside the eventual closure of coal-fired power stations, could push prices back up.”