Datacenter power consumption in the United States is growing roughly ten times faster than the country's electricity grid capacity. Insurance broker Howden calculates that datacenters would need to source up to 58% of their power off the grid by 2030 to keep their share of grid capacity from growing.
The finding exposes long-term underinvestment in the US grid networks required to deliver power to the growing number of server farms. Howden's analysis of data from the US Energy Information Administration and S&P Global found that electricity supply to datacenter campuses has risen 19% a year on average since 2000, while grid capacity expanded by just 2% annually over the same period. Datacenters' share of US grid capacity increased from 0.1% in 2000 to about 5% in 2025, a 50-fold expansion.
The surge is driven by the build-out of AI computing capacity. Gartner warned in June that AI datacenter energy consumption is on track to rise 26% this year, and that grid supply may be unable to keep pace by the end of the decade. Management consultancy Bain & Company, in a report two years ago, forecast that energy draw by server farms would more than double by 2030 and called on energy companies to accelerate grid investments.
Howden estimates that keeping datacenters at 5% of grid capacity would require 110 gigawatts of behind-the-meter power by 2030, an expansion it considers unlikely. Instead, the broker expects a combination of greater reliance on the grid, slower development at power-constrained sites, and alternative supplies. For the largest, most power-constrained projects, grid delays of two to six years could mean $800 million to $2.4 billion in forgone revenue.
"Power availability is becoming one of the defining challenges of the datacenter boom," said Stuart Adam, head of Natural Resources at Howden. "As demand for AI infrastructure accelerates, developers are increasingly looking beyond traditional grid connections to secure the electricity they need."
Adam noted that on-site generation introduces new operational and financial exposures, as operators take on greater responsibility for their power infrastructure.
Analysis
Why This Matters
- Grid constraints could slow AI deployment and raise costs for tech companies and consumers.
- The imbalance underscores chronic underinvestment in US energy infrastructure that may affect other industries.
- A shift toward on-site generation brings new safety, insurance, and regulatory challenges.
Background
The rapid expansion of AI has driven a surge in datacenter construction, particularly in the United States. Datacenters require vast amounts of electricity to power servers and cooling systems. The US electricity grid has historically operated with ample capacity, but the pace of demand growth from datacenters is now outstripping investment in new transmission and generation.
What to Watch
- How quickly grid expansion projects can be permitted and built to meet growing demand.
- Whether datacenter operators will increasingly turn to behind-the-meter gas, solar, or nuclear power.
- The response from US energy regulators and policymakers to the emerging supply-demand imbalance.
Checked
11 claims in this story checked against 1 source: 8 supported.
Show each claim
- Partly supportedUS datacenter power demand grows ten times faster than grid capacity.www.theregister.com - Articles: “Datacenter power consumption in the US is growing roughly ten times faster than grid capacity”
- SupportedHowden analysis finds datacenters may need to source up to 58% of their power off-grid by 2030 to keep their share of grid capacity from growing.www.theregister.com - Articles: “Howden calculates that datacenters would need to source up to 58 percent of their power off the grid by 2030 just to keep their share of grid capacity from growing.”
- SupportedUS datacenter power consumption is growing roughly ten times faster than the country's electricity grid capacity.www.theregister.com - Articles: “Datacenter power consumption in the US is growing roughly ten times faster than grid capacity”
- SupportedThe finding exposes long-term underinvestment in US grid networks needed to deliver power to growing numbers of server farms.www.theregister.com - Articles: “Surging demand for AI infrastructure is driving a wave of new server farms across America, but it is exposing long-term underinvestment in the grid networks required to deliver power where it's needed.”
- SupportedSince 2000, electricity supply to datacenter campuses has risen 19% a year on average, while grid capacity expanded by 2% annually.www.theregister.com - Articles: “since the year 2000, power being fed to data campuses has risen 19 percent a year on average, while the electricity grid expanded capacity by just 2 percent per annum over the same period.”
- SupportedDatacenters' share of US grid capacity increased from 0.1% in 2000 to about 5% in 2025, a 50-fold increase.www.theregister.com - Articles: “Datacenters' share of US grid capacity was circa five percent in 2025, up from 0.1 percent in 2000 – a 50-fold increase.”
- SupportedGartner warned in June that AI datacenter energy consumption is on track to rise 26% this year and grid supply may be unable to keep pace by the end of the decade.www.theregister.com - Articles: “Gartner warned in June that the energy consumed by AI datacenters is on track to grow 26 percent this year, and grid supply may be unable to keep pace with demand by the end of this decade.”
- Partly supportedHowden estimates that keeping datacenters at 5% of grid capacity would require 110 gigawatts of behind-the-meter power by 2030.www.theregister.com - Articles: “Keeping datacenters at five percent of grid capacity requires 110 gigawatts of behind-the-meter capacity by 2030, Howden estimates”
- Partly supportedFor the largest, most power-constrained projects, grid delays of two to six years could mean $800 million to $2.4 billion in forgone revenue.www.theregister.com - Articles: “For the largest, most power-constrained projects, Howden warns that grid delays of two to six years could mean $800 million to $2.4 billion in forgone revenue.”
- SupportedStuart Adam said, “Power availability is becoming one of the defining challenges of the datacenter boom,” and is Howden's head of Natural Resources.www.theregister.com - Articles: “"Power availability is becoming one of the defining challenges of the datacenter boom," says Howden head of Natural Resources Stuart Adam.”
- SupportedStuart Adam said, “As demand for AI infrastructure accelerates, developers are increasingly looking beyond traditional grid connections to secure the electricity they need.”www.theregister.com - Articles: “"As demand for AI infrastructure accelerates, developers are increasingly looking beyond traditional grid connections to secure the electricity they need."”