Bathla Group collapse leaves Sydney home buyers facing unfinished developments

Construction halted at dozens of sites as investors race to find builders

By LineZotpaper
Published
Updated
Read Time3 min
Sources3 outlets
Follow this storyHear when it moves
The collapse of developer Bathla Group stopped work at 45 sites, and experts say delays or failures could leave some communities 'almost wastelands'.

Rinnah Roque, 60, bought a three-storey townhouse off the plan in Box Hill, in Sydney's north-west, hoping to live in a community. Instead, construction on the development across the road stopped two months ago after the developer Bathla entered administration. 'All of a sudden everything stopped, and what's so frustrating is everything was just left behind,' she said. Roque said it would be a 'horror story' if the area became a wasteland.

Bathla Group went into administration in August, in a $3.4 billion collapse. According to documents filed by administrator Teneo in the NSW Supreme Court, construction stopped at 45 sites. About a dozen of these are in Sydney's west, in suburbs including Marsden Park, Box Hill, Rouse Hill and Pemulwuy.

Lyndall Bryant, a property economics professor at Queensland University of Technology, said builders considering finishing the projects would find it difficult to assess the quality of work already done. 'If you're a builder coming into a job that's half-finished, you don't want to be warranting the work that someone else has done,' she said. She said delayed or failed projects could leave communities 'fractured' and 'those areas really could become almost wastelands for a number of years', bringing down property values.

Urban Taskforce Australia chief executive Tom Forrest said he believed most projects would be completed. 'Where I would be concerned is if we were to find developments with substantial defects, where basically the cost to rectify those defects is greater than the value of the land with an approval on it,' he said. Urban Taskforce Australia said any drop in property values would be a 'short-term blip'.

Two Sydney councils are among the most exposed. Construction stopped on eight Bathla projects in Blacktown Council and four in The Hills Shire Council. Both councils are registered as creditors. Bryant said councils might have to spend money on infrastructure such as roads and sewage that Bathla had yet to contribute to, and would miss out on anticipated rate revenue unless the developments are finished. Blacktown Council declined a request for comment. The Hills Shire Council mayor, Michelle Byrnes, said the collapse was 'another hit to public confidence in the construction industry'. 'I'm devastated for the buyers across Sydney who have been left stranded by Bathla's collapse,' she said.

Some private equity investors have seized control of the sites they funded and are racing to finish them. Asian private equity company PAG appointed builder ParkView to its 300-unit development in Pemulwuy. Ray White Capital, which owns the Box Hill site, expects it to be finished before April 2027. Leda Group has taken control of a 240-unit development in Marsden Park and said it was in advanced discussions with a builder. But not all sites have been taken over. Among them is a 49-home estate in Lochinvar in the Hunter Region, where restructuring firm Mackay Goodwin has been appointed to assess options.

RSS

The Daily Edition

The front page in your inbox each weekday morning: the lead, the picks, and why each one earned its place.

Weekday mornings. We email a six digit code to check the address is yours. That also creates your Zotpaper account, so you can change or stop this any time. One-click unsubscribe in every issue. Privacy.

§

Analysis

Why This Matters

  • Home buyers who paid deposits off the plan face prolonged uncertainty and potential loss of value if developments are not completed.
  • Councils in Sydney's growth areas could be left to fund infrastructure for partially built suburbs, straining budgets.
  • The collapse adds to falling confidence in the construction industry, which may affect future housing supply in high-demand regions.

Background

Bathla Group was a residential developer active in Sydney's north-west and western growth corridors. It entered administration in August 2026 owing $3.4 billion, halting construction at dozens of sites. The company declined the ABC's requests for comment. Administrators are working to sell or complete the projects, with some investors taking direct control.

Key Perspectives

Rinnah Roque (Box Hill home buyer): Says she worked hard to buy a property for herself and her mother, and is frustrated that construction has stopped, leaving an unfinished site across the road. She called the prospect of a wasteland a 'horror story'.

Lyndall Bryant (QUT property economics professor): Warns that builders may be reluctant to guarantee half-finished work, risking sites languishing. She says delayed or failed projects could create 'wastelands' for years, lowering property values for existing residents.

Tom Forrest (Urban Taskforce Australia): Believes most projects will be completed and that any drop in property values will be a 'short-term blip'. He says concerns would arise only if defects cost more than the land is worth.

Michelle Byrnes (The Hills Shire Council mayor): Says the collapse is 'another hit to public confidence' and that she is 'devastated' for buyers left stranded.

What to Watch

  • Whether builders can be found to finish the remaining sites, especially those not taken over by creditors.
  • The timeline for completion of sites under new management, such as Box Hill (target April 2027).
  • Potential financial strain on Blacktown and Hills Shire councils as they seek to recover debts and fund infrastructure.

Sources

Checked

12 claims in this story checked against 1 source: 10 supported.

Show each claim
  1. SupportedBathla Group’s collapse leaves Sydney home buyers facing unfinished developments.Latest business news: “The residential development dividing Hynds Road is one of hundreds caught up in the $3.4 billion collapse of Bathla Group. And it is among dozens of sites that were part way through construction when the money stopped flowing.”
  2. SupportedConstruction halted at dozens of sites.Latest business news: “it is among dozens of sites that were part way through construction when the money stopped flowing.”
  3. SupportedInvestors are racing to find builders to finish projects.Latest business news: “the private equity companies that are owed money by Bathla have taken control of the projects they invested in, and are racing to find builders that will finish them.”
  4. Partly supportedExperts say delays or failures could leave some communities “almost wastelands”.Latest business news: “Professor Bryant said the delay or failure of a project in these locations could leave communities "fractured". "Those areas really could become almost wastelands for a number of years," she said.”
  5. SupportedConstruction stopped at 45 Bathla sites.Latest business news: “Bathla was forced to stop construction at 45 sites after it was placed into administration in August, according to documents filed by the administrator Teneo to the NSW Supreme Court.”
  6. SupportedBathla went into administration in August.Latest business news: “Bathla was forced to stop construction at 45 sites after it was placed into administration in August”
  7. SupportedThe collapse was worth $3.4 billion.Latest business news: “The residential development dividing Hynds Road is one of hundreds caught up in the $3.4 billion collapse of Bathla Group.”
  8. SupportedRinnah Roque, 60, bought a three-storey townhouse off the plan in Box Hill.Latest business news: “The 60-year-old, committed to a growing community in Sydney's north-west, bought a three-storey townhouse off the plan in Box Hill.”
  9. SupportedRoque said, “All of a sudden everything stopped, and what's so frustrating is everything was just left behind.”Latest business news: “"All of a sudden everything stopped, and what's so frustrating is everything was just left behind," she said.”
  10. SupportedConstruction across the road stopped two months ago after Bathla entered administration.Latest business news: “Construction work on Hynds Road stopped after Bathla entered administration. [...] But for the past two months, the symphony of construction noise has been replaced by silence.”
  11. SupportedBryant said, “If you're a builder coming into a job that's half-finished, you don't want to be warranting the work that someone else has done.”Latest business news: “"If you're a builder coming into a job that's half-finished, you don't want to be warranting the work that someone else has done," she said.”
  12. Partly supportedConstruction stopped on eight Bathla projects in Blacktown Council and four in The Hills Shire Council.Latest business news: “Construction had stopped on eight Bathla projects in Blacktown Council, and at four sites in The Hills Shire Council.”