Coalition says SRL pause won't stop tunnelling as $1b cost warning emerges

Opposition says tunnel boring will continue during review, against industry expectations, as a briefing note estimates a material pause would cost $1 billion to $1.5 billion

By LineZotpaper
Published
Read Time3 min
Sources3 outlets
Follow this storyHear when it moves
The Victorian Coalition has clarified its promise to pause and review the Suburban Rail Loop will not stop tunnel boring or send workers home, after five government sources said a material pause would cost at least $1 billion.

Construction of the $34.5 billion underground rail line will continue if the Coalition wins the state election, an opposition spokesperson said, despite industry expectations that the policy meant a halt to work.

The Suburban Rail Loop was promised by former premier Daniel Andrews before the 2018 election and has been a key issue in successive campaigns. Tunnel boring is under way on the SRL East line from Cheltenham to Box Hill, with three machines having dug 138 metres since September.

A briefing note provided to the state government in recent months estimated that anything other than a minor pause would cost $1 billion to $1.5 billion, according to five government sources who spoke anonymously to detail confidential documents. A six-month delay in SRL East construction after tunnel boring began would cost between $2.2 billion and $2.7 billion, the note said.

The Coalition spokesperson rejected the figures, saying the independent Parliamentary Budget Office had assessed the party's policy and found it would have no impact on the budget position. "The Coalition position to pause and review the SRL does not mean workers are sent home or tunnel boring stops," the spokesperson said. "Anything that purports to cost our policy on this basis is a lie and misleading."

The sources conceded the advice was partly informed by people with an interest in keeping the project going, such as Suburban Rail Loop Authority staff, but said many issues were valid. They noted that best-practice guidelines mean tunnel boring machines should not be paused for extended periods under housing, requiring them to reach a suitable location before stopping. Contractors are also entitled to compensation during a suspension, confirmed by the Victorian Auditor-General's Office, which stated the state must pay reimbursable costs even if it suspends the contract. Exceptions apply if the suspension is because of an issue created by the contractor or if the authority determines the project is late or over budget.

Opposition Leader Jess Wilson has repeatedly cast doubt on the total cost estimate, citing blowouts on other projects and high construction inflation. "The only responsible thing to do for an incoming government that has no visibility of the contracts that have been signed is to pause this project to make sure we do a review that is swift," she said at The Age's Melbourne Assembly. "Then we make a decision in the best interest of Victorians, taking into account the contractual arrangements, the financing arrangements, and of course, the construction at that point in time."

The Coalition spokesperson said its commitment to pause had no technical or budgetary differences from the government’s decision not to award further SRL contracts until its review was complete. The Labor government has announced $1 billion in savings and committed to a technical review to find another $1 billion.

The state's economic and fiscal update, to be released on Friday, will show operating surpluses of $300 million in 2026-27 and 2027-28, down from forecasts in the May budget, which projected surpluses starting at $1 billion and rising to $2 billion by 2030. Net debt is now expected to reach $197 billion by 2030, $2.3 billion lower than previously forecast. The government will say the lower debt and continued surpluses show its efforts to reduce spending have been working.

RSS

The Daily Edition

The front page in your inbox each weekday morning: the lead, the picks, and why each one earned its place.

Weekday mornings. We email a six digit code to check the address is yours. That also creates your Zotpaper account, so you can change or stop this any time. One-click unsubscribe in every issue. Privacy.

§

Analysis

Why This Matters

  • The SRL is the largest public transport project in Victoria's history, and any change in its scope or timeline directly affects thousands of construction workers, commuters in the south-east, and the state budget.
  • The cost dispute highlights the high stakes of election commitments on major infrastructure: taxpayers face billions in penalties if contracts are paused, while campaign promises may be constrained by existing legal obligations.
  • The election outcome will determine whether the project proceeds on its current timetable (trains by 2035) or faces a review that could alter its route, stations, or overall cost.

Background

The Suburban Rail Loop is a 26-kilometre underground rail line connecting Cheltenham to Box Hill via Glen Waverley and Monash. First proposed by then-premier Daniel Andrews in 2018, it is being delivered in stages, with the Melbourne east section, SRL East, currently under construction. The project's total cost was estimated at $34.5 billion in 2020, though the Coalition argues this is likely to rise. Tunnel boring began in September 2026, and about 1,750 people are employed on the project.

Key Perspectives

Coalition (Jess Wilson and spokesperson): The "pause and review" commitment does not mean stopping work; tunnel boring and contracts in progress will continue. The independent Parliamentary Budget Office found the policy has no budget impact. The Coalition says it will be transparent about the true cost of the project.

Labor (Premier Ben Carroll, Treasurer Colin Brooks): The government has already found $1 billion in savings and commissioned a technical review for another $1 billion. It has delayed signing two station-building contracts until the review is complete. Brooks says the government's "commonsense decisions" have preserved budget surpluses.

Anonymous government sources: The advice to government is that a material pause would cost $1 billion to $1.5 billion; six months' delay after boring started could cost $2.2 billion to $2.7 billion. Sources noted that tunnel boring machines cannot be paused under housing and contractors are entitled to compensation during suspension.

What to Watch

  • The Victorian economic and fiscal update on Friday, which will provide updated budget figures and may influence the campaign's economic narrative.
  • Whether the Coalition releases its own cost analysis of the SRL before election day, as Wilson has promised transparency.
  • The timing of the two station-building contracts that Labor has delayed; if they remain unsigned through the caretaker period, the next government will have immediate decisions to make.

Sources

Checked

11 claims in this story checked against 1 source: 9 supported.

Show each claim
  1. SupportedThe Coalition says pausing and reviewing the SRL would not stop tunnel boring or send workers home.WA Today - Latest News: ““The Coalition position to pause and review the SRL does not mean workers are sent home or tunnel boring stops,” the spokesperson said.”
  2. SupportedA briefing note estimated a material pause would cost $1 billion to $1.5 billion.WA Today - Latest News: “The Age can reveal a briefing note provided to the state government in recent months estimated anything other than a minor pause would cost $1 billion to $1.5 billion.”
  3. SupportedThe briefing note’s warning emerged alongside the Coalition’s position that tunnelling would continue.WA Today - Latest News: “The figures have prompted the Coalition to clarify its position to pause and review the project. An opposition spokesperson confirmed drilling would continue during this process”
  4. SupportedThe policy had been interpreted by the construction industry to mean construction would halt during the review.WA Today - Latest News: “The Coalition’s position on the SRL had previously been interpreted by the construction industry to mean a halt to construction while contracts for the project were reviewed.”
  5. Reports differThe SRL is described as a $34.5 billion underground rail line.WA Today - Latest News: “the $33.5 billion underground line is a key issue. ... Wilson has repeatedly cast doubt on the project’s total cost estimate of $34.5 billion, announced in 2020”
  6. SupportedThree tunnel boring machines have dug 138 metres since September.WA Today - Latest News: “There are three tunnel boring machines digging under Melbourne’s south-east, which collectively have dug 138 metres of tunnel since September.”
  7. Partly supportedA six-month construction delay after tunnel boring began would cost $2.2 billion to $2.7 billion, according to the briefing note.WA Today - Latest News: “A six-month delay in the construction of SRL East – after tunnel boring machines began drilling the Cheltenham to Box Hill line last month – would hit taxpayers with a bill of between $2.2 billion and $2.7 billion.”
  8. SupportedThe Coalition spokesperson said the policy was assessed by the Parliamentary Budget Office as having no impact on the state budget position.WA Today - Latest News: ““The independent Parliamentary Budget Office has assessed our policy to pause and review the Suburban Rail Loop and found it will have no impact on the state’s budget position.””
  9. SupportedThe Auditor-General’s Office said the state must pay reimbursable contractor costs during a contract suspension.WA Today - Latest News: ““If the state suspends the contract it is still required to pay the reimbursable costs of the contractor during the period of contract suspension.””
  10. SupportedThe Victorian economic and fiscal update would show operating surpluses of $300 million in 2026-27 and 2027-28.WA Today - Latest News: “On Friday, the Victorian economic and fiscal update, details of which were provided to The Age before its publication in full, will show operating surpluses of $300 million in 2026-27 and 2027-28”
  11. SupportedNet debt was expected to reach $197 billion by 2030, $2.3 billion lower than forecast.WA Today - Latest News: “Despite this, net debt will be $2.3 billion lower than forecast in 2030 and is now expected to reach $197 billion.”