The long-awaited M1 metro extension to Bankstown opens on Friday, ending more than two years of disruption for southwest Sydney residents and capping a project that saw cost estimates nearly double to $23 billion for the full Chatswood-to-Bankstown line.
The final stretch converts a 130-year-old heavy rail line into a driverless metro, a task that can be harder than building a new line over paddocks or beneath a city. Plans drawn up last decade were scaled back after it became clear how challenging and expensive the conversion would be. Plans to straighten curved platforms were dropped; Sydney Metro customer and operations head Hugh Lawson said straightening them would have required moving some stations further down the track.
The closure disrupted up to 60,000 commuters who had used the T3 heavy rail line each day. The bill for replacement buses was about $200 million. Campsie café worker Aayusha Thakuri said catching them made a one-way trip into the CBD almost 90 minutes long on occasions.
Premier Chris Minns this week disclosed that the southwest section alone cost $10 billion, making the combined Chatswood-to-Bankstown project nearly $23 billion, double the forecast of about $11.5 billion when plans were unveiled last decade. The government poured in an extra $1.1 billion after winning the 2023 election to finish the job, but was forced to add more last year.
At Campsie, café worker Aayusha Thakuri said the past two years had been hard: “I just wasted my three hours travelling [for a return trip to the central city].” Butcher Wren Zhang, who has lived in the suburb for 35 years, said the metro would bring a “very good future” and that “we need more people coming.” Belmore Cakes owner Anastasia Varsamas, who is fighting high-rise developments, said, “We’re a small community. I’d like for it to stay this way.” Her business had a drop of at least 20 per cent in trade during the rail closure, and she hopes the metro will improve business.
Experts see significant economic potential. Martin Locke, an adjunct professor at Sydney University’s Institute of Transport and Logistics Studies, said the key challenge was to “realise value from upgraded transport links” and warned against “cutting the ribbon on it” without long-term land-use planning. Eamon Waterford, chief executive of the Committee for Sydney, forecast an “explosion in profitable” cultural businesses in the multicultural south-west and said job creation would likely far exceed official forecasts.
The project was nearly cancelled several times. Labor policy under leader Luke Foley before the 2019 election was to scrap the conversion; a 2020 parliamentary inquiry recommended it be ditched as not value for money; and senior figures in the Perrottet government debated abandoning it in late 2022. The Minns government commissioned a review after the 2023 election before later committing to the conversion.
Lawson, who worked on the London Overground before joining Sydney Metro, said the difficulties of working with a 130-year-old railway had produced unexpected finds: “You’re digging into a platform that’s had 100 years of who knows what going on.” He expected locals to use the south-west line for short trips between suburbs as much as for travel into the CBD, and said Campsie station would be busy all day every day. He said the decade of work was “just getting to the start line” of the changes the metro would bring over years and decades.
Analysis
Why this matters
- The opening returns a fast, high-frequency rail service to more than 60,000 daily commuters in Sydney’s south-west who endured two years of replacement buses.
- The project’s cost blowouts and long delays make it less likely that other sections of Sydney’s heavy rail network will be converted to metro standards, shaping the city’s transport future.
- The metro is expected to drive higher-density housing and economic activity along the corridor, but local businesses and residents remain divided over the pace and scale of redevelopment.
Background
The M1 metro extension to Bankstown is part of a larger project to link Sydney’s north-west and south-west through a driverless rail line. Originally conceived in the early 2010s, the conversion of a 130-year-old heavy rail line proved more difficult and expensive than building a new line from scratch. Plans were scaled back in 2018, but the project still ran years late and more than double its initial budget. The line’s opening on Friday ends two years of disruption for commuters who relied on replacement buses.
Key perspectives
- Hugh Lawson (Sydney Metro): Described the conversion as a “first test of practicality” and noted that straightening curved platforms would have required moving entire stations from community centres. He said the opening is “just getting to the start line” of the changes the metro will bring.
- Martin Locke (Sydney University): Argued the key challenge is to “realise value from upgraded transport links” and that planners must create local jobs and economic clusters beyond residential development.
- Eamon Waterford (Committee for Sydney): Predicted an “explosion in profitable” cultural businesses in the south-west and said job creation will likely be significantly higher than official forecasts due to improved connectivity.
- Anastasia Varsamas (Belmore Cakes owner): Opposed high-rise development, wanting Belmore to remain a “small community,” but hoped the metro would boost her trade, which fell 20 per cent during the rail closure.
- Wren Zhang (Campsie butchery owner): Welcomed the metro’s “very good future” for the suburb and said “we need more people coming” to support business.
- Aayusha Thakuri (Campsie café worker): Expressed relief that the metro opening would end her daily three-hour round trips during the rail closure.
What to watch
- Ridership numbers in the first months, which will test the service’s capacity and reliability.
- The pace of residential and commercial development along the corridor, particularly around stations like Campsie and Bankstown.
- Any further government decisions on converting other heavy rail lines to metro, given the difficulties encountered on this project.
Checked
12 claims in this story checked against 1 source: 11 supported.
Show each claim
- SupportedSydney’s M1 metro extension to Bankstown opens after long delays and cost blowouts.Sydney Morning Herald - Latest News: “As the long-awaited M1 extension to Bankstown opens on Friday, we take a look at how it happened and what it means for the city.”
- SupportedThe conversion of the 130-year-old rail line cost $10 billion.Sydney Morning Herald - Latest News: “this week Premier Chris Minns disclosed that the Southwest Metro cost $10 billion”
- SupportedThe shutdown disrupted commuters for more than two years.Sydney Morning Herald - Latest News: “a year, and later about 18 months before becoming more than two years.”
- SupportedThe full Chatswood-to-Bankstown project cost nearly $23 billion, almost double the forecast of about $11.5 billion.Sydney Morning Herald - Latest News: “cost nearly $23 billion combined. That is double the forecast of about $11.5 billion when plans were unveiled last decade.”
- SupportedThe closure disrupted up to 60,000 people who used the T3 line each day.Sydney Morning Herald - Latest News: “up to 60,000 commuters who had used the T3 heavy rail line each day.”
- SupportedThe replacement-bus bill was about $200 million.Sydney Morning Herald - Latest News: “The bill for putting on pink-coloured replacement buses to ferry commuters along the corridor during the two-year rail shutdown alone is about $200 million.”
- SupportedThakuri said replacement buses sometimes made her one-way trip to the CBD almost 90 minutes long.Sydney Morning Herald - Latest News: “For the past two years, the need to catch replacement buses has made a one-way trip into the CBD almost 90 minutes long on occasions.”
- Partly supportedWaterford said job creation would likely far exceed official forecasts.Sydney Morning Herald - Latest News: “Eamon Waterford, chief executive of urban policy think tank and lobby group Committee for Sydney, predicts a significantly higher number of jobs will be created than forecast in the business case.”
- SupportedThe project was nearly cancelled several times, including after a 2020 parliamentary inquiry recommended ditching the conversion as not value for money.Sydney Morning Herald - Latest News: “A year later, a parliamentary inquiry into the Southwest Metro project recommended in 2020 that the government ditch the Bankstown line’s conversion, arguing it was not value for money”
- SupportedLawson said: “You’re digging into a platform that’s had 100 years of who knows what going on.”Sydney Morning Herald - Latest News: ““You’re digging into a platform that’s had 100 years of who knows what going on.””
- SupportedLawson said straightening curved platforms would have required moving some stations further down the track.Sydney Morning Herald - Latest News: ““In some locations … you would have had to move the entire station, the heart of the community, further down the track to somewhere where it was actually possible to straighten the track,” he explains.”
- SupportedLawson expected Campsie station to be busy all day every day.Sydney Morning Herald - Latest News: ““Campsie is a great example of that. This station will be busy all day every day,” he says.”